Workdays effort
magnus.sundstrom
#1 Posted : Wednesday, April 30, 2014 10:25:35 AM

Posts: 91

We're using Schedule8X5 and we need the effort column and its editor to show work days, not 24 h days. It turns out it's very confusing for people that the effort and end date are calculated using 8 hour workdays, but the effort is actually displayed as "24 hour days.hh.mm.ss". How?

Also - this might be a beginner question - but we need to get rid of the minutes and seconds part of the effort, both in the column and in the editor. How?
Raja - RadiantQ
#2 Posted : Friday, May 02, 2014 11:12:09 AM

Posts: 314

Magnus,

How would you like to show the effort column in the Gantt? Can you tell us with some example values, and how does it needs to show and behave?
Thanks & Regards,
Rajagopal.
magnus.sundstrom
#3 Posted : Saturday, May 03, 2014 6:12:49 AM

Posts: 91

We're coverting it to this format now, using the standard effortToString way: "1 d 5 h". Problem is that 1 d means 24 hours and we need it to be 8. Also the editor should show the same format (or 'd.h' if that's not possible) and take the schedule into account as well. The effort also needs to be displayed in this same format in the popups when hovering over taskbars.
Bala - RadiantQ
#4 Posted : Monday, May 12, 2014 8:42:32 AM

Posts: 393

Magnus,

Could you please take a look at our ..Samples/RoundTimesToDay8X5.htm install sample, in that sample we show how to display the effort based on the Schedule.
Bala,
RadiantQ
Tag as favorite
Forum Jump  
Please Email support@radiantq.com for any issues

ugg boots outlet cheap ugg sale ugg boots clearance ugg boots sale ugg boots cheap ugg boots for women uggs for cheap ugg shops cheap ugg boots cheap uggs Official Ugg Outlet ugg Store Buy Cheap UGGs ugg boots uk ugg boots usa ugg Online uggs on sale ugg outlets cheap ugg boot Discount UGG Boots discount uggs